Updated: 28 November 2015    Full page map    Chengdu BRT photos

Chengdu
Peak throughput (passengers / hr / direction): 9,320  South of Hongpailou Dong, AM peak, N-S, 2015.11.25    [ITDP survey]
Year system commenced: 2013  Opened 11 June (trial operation from 31 May)   
System name: CDBRT   
Number of BRT stations: 29   

Performance

Peak throughput (passengers / hr / direction): 9,320  South of Hongpailou Dong, AM peak, N-S, 2015.11.25    [ITDP survey]
Peak buses / hr / direction: 101  Hongpailou Dong, AM peak N-S, 25-Nov-15    [ITDP survey]
City centre peak hour speed: 30 km/hr  Multiple AM & PM surveys, 2015.11.24-25    [ITDP survey]
Full corridor peak hour speed: 30 km/hr  Multiple AM & PM surveys, 2015.11.24-25   
BRT system coverage (2-way roads) (1 fare): 29.8 km   
Operational mode: trunk-only   
Routes operating both inside & outside BRT roads: 0   
Routes operating only in busway corridors: 4  K1, K2, K1A, K2A   
Average bus occupancy (peak direction & point): 93   
Highest peak hour boardings at a single station: 1,660  31-Jul-2013, PM peak, Hongpailoudong station   
Network of routes and corridors   
High peak period operational speed (>20km/hr)   
Faster than a trotting donkey   
Buses operating both in & out of BRT corridors   
Most bus passengers in BRT corridors carried by BRT buses   
Net time saving for bus passengers in corridor   
Throughput >20,000 passengers/hr (one direction)   
Throughput >10,000 passengers/hr (one direction)   
Carries more than a mixed traffic lane (2500 pphpd)   

Vehicles & ITS

Fleet of special BRT buses: 232  164 initially, increased to 232 in 2015. 18m buses   
Fleet of regular buses using BRT stations: 0   
Fleet of 18m or larger BRT buses: 232   
Fleet of integrated BRT feeder buses: 0   
Type of fare collection / verification technology: Card, token   
Location of bus doorways: Both sides  traffic is on the right   
Number of doors in BRT buses: 5  2 left side, 3 right side; stations use left side   
BRT vehicle length: 18m   
No. of seats in 18m BRT buses: 38   
BRT vehicle fuel: CNG   
BRT bus manufacturer: Shudu   
Fare system vendor: Jiangsu Huimin   
Sliding door system vendor: Jiangsu Huimin   
Real-time next bus information displays   
Distinctive BRT buses   
Sliding doors in BRT stations   
Low-emission vehicle technology (≥Euro III)   
Automated fare collection and fare verification   
System control centre   
High-quality passenger information on buses   
Audio announcements on BRT buses   
Real-time CCTV surveillance at all stations   

Other

BRT Standard score (GOLD, SILVER, BRONZE): SILVER   
Year system commenced: 2013  Opened 11 June (trial operation from 31 May)   
System name: CDBRT   
Lead local design / planning work: Chengdu Municipal Engineering Design Research Institute   
Distinctive marketing identity for system   


Infrastructure

Number of BRT stations: 29   
Stations with functioning passing lanes: 0   
Most station substops: 1   
Location of busway lanes: Centre of roadway on elevated road   
Longest BRT station (non terminal): 161m   
Shortest BRT station: 73m   
Total length of dedicated busway: 29.8 km   
Length including mixed traffic portions: 29.8 km   
Station platform width (including walls & doors): 5m   
Station platform height: 35cm   
Average distance between stations: 1,020m   
Number of corridors: 1  Circular corridor   
Number of BRT terminals: 1   
Number of BRT depots: 2   
Segregated busways or bus-only roadways   
Enhanced station (more than just a bus shelter)   
Overtaking lanes at more than 75% of stations   
Bike sharing in vicinity of BRT stations   
Wheelchair accessible stations   
Distinctive BRT stations   
>1 substop at >75% of stations (requires overtaking)   
Includes BRT-only tunnels or bridges   
>1 stop position at stopping area at >75% of stations     4 station doors can accommodate 2 18m buses
Stations away from intersections   
Station size based on passenger demand   
Full weather protection on most station platforms   
Full weather protection on all station platforms   
Covered station access     Station access bridges are not covered
Escalators/lifts at >20% of stations with bridges/tunnels   
Signal priority or grade separation at intersections   
Level boarding and alighting   
High-quality passenger information at stations   
Bicycle parking at BRT stations     Despite huge bicycle volumes
Segregated bike lanes along main corridor(s)   
Improvements to nearby public space     Massively degraded via elevated road
Physical BRT laneway dividers   

Regulation & costs

Fare type (flat fare or distance-based): flat fare  Distance based set-up, though, with exit verification   
Median cash fare: 2 yuan  3 yuan after 10pm   
Median smart card fare: 1.8 yuan  2.7 after 10pm; monthly pass: 1 yuan and 3 times free transfer in 2 hrs   
BRT bus operator(s): Chengdu Public Transport Group CO., LTD   
BRT management agency: Chengdu Public Transport Group   
Operating hours: 5:50am-11.48pm  K1: 6:18-23:48, K2:5:50-23:08, K1A/K2A:7:00-19:00, K2A:7:00-19:00 K2:5:50-23:08 K1A/K2A:7:00-19:00) K2A:7:00-19:00   
More than one BRT bus operator   
Pre-board fare collection and fare verification   
Competitively bid operating contracts   
Payment per bus-kilometre rather than per passenger   
No operational subsidy from government     subsidy needed
BRT authority plans and controls the system   